Energy: The power push in Zambia and Zimbabwe

The third Zimbabwe-Zambia Energy Projects Summit (Zim-Zam 2026) took place from 3-5 November 2026 in Livingstone, Zambia. The Bowmans expert pan-African team who were in attendance share their key takeaways from this year's Summit, which had the theme “Celebrating How Zambia and Zimbabwe Have Unlocked FDI Through Connectivity, Credibility and Cooperation".

OPINION

The Zimbabwe-Zambia (Zim-Zam) Energy Projects Summit took place from 3 to 5 November 2026 at Livingstone’s Radisson Blu Mosi-oa-Tunya. Organised by EnergyNet and hosted by Copperbelt Energy Corporation (CEC), the summit aimed to connect ambitions for foreign investment with the themes of connectivity, credibility, and cooperation. Bowmans was proud to be the lead sponsor.

Our team at the summit shared the following key takeaways from the discussions.

Installed capacity is misleading

Zambia’s installed generation capacity is approximately 4 722 MW, including more than 1 027 MW of solar. Zimbabwe’s private-generation pipeline comprises 635 MW under construction and another 730 MW approaching financial close.

These are different investment milestones, not equivalent measures of available electricity. Installed capacity does not guarantee reliable output, while pipeline projects face financing and construction risks.

While investment is flowing into generation, transmission requires greater attention. Without reliable connections to demand centres, new power plants cannot fully support production growth.

Capital follows credible revenues

Domestic bonds, project loans and foreign direct investment (FDI) are distinct funding sources. Green bonds also have a role to play in raising debt for eligible environmental projects and broadening funding beyond conventional bank loans. CEC’s green-bond financing is an example of how local capital can be mobilised alongside international investment.

However, green bonds do not eliminate commercial risk. Repayment depends on revenues and the issuer’s financial strength, while currency mismatches can persist where borrowing, equipment costs and electricity sales are denominated in different currencies.

Independent power producers (IPPs) similarly depend on credible customers and enforceable power purchase agreements (PPAs). A signed contract reassures lenders only if the buyer can pay and the network can deliver.

Expanding the customer base beyond dollar-earning mines to include manufacturers, other enterprises and prepaid consumers could diversify revenues. Financing structures must, however, reflect the different payment risks associated with these customers.

Completed projects demonstrate developers’ ability to deliver, strengthening their credibility and potentially improving access to debt for subsequent phases.

Private supply needs strong networks

Industrial customers are increasingly developing their own generation capabilities. Yet self-supply does not eliminate dependence on the network. Businesses must assess backup requirements, operating hours, grid charges and the implications of curtailed output, rather than focusing solely on headline tariffs.

Open access, which allows eligible producers and customers to trade electricity through the network, can broaden competition. Its value depends on transparent rules, fair charges and reliable system operation.

Credibility must become a delivery discipline

Regulatory credibility must be demonstrated through implementation.

  • For governments and regulators, this means transparent project pipelines, predictable approvals and workable open-access rules.

  • For utilities, it means clearer information on available capacity, reliable network services and tariffs that support sustainable operations while taking industrial competitiveness into account.

  • For developers and financiers, the next test is to translate prospective demand into enforceable contracts, and projects with realistic construction schedules. Transmission investment must advance alongside generation, with clear responsibilities and explicit dependencies among projects.

On day two, the discussions centred on the fact that, although regional power trading and domestic capital offer pathways to investment, financing gaps and transmission bottlenecks remain the decisive test. Both countries need stronger electricity networks and credible payment arrangements to turn proposed power projects into reliable supply.

Domestic capital as a bridge to foreign investment

Governments’ role is to create an environment conducive to investment. However, there is a persistent financing tension: financiers seek payment security, while governments remain cautious about providing guarantees.

Public-private financing and domestic capital emerged as potential ways to bridge the financing gap. Projects involving domestic banks and pension funds tend to attract foreign investment more readily, suggesting that local participation could strengthen international confidence.

The implication is clear: attracting external capital and mobilising domestic resources are complementary strategies. A combination of pension-fund investment, domestic resource mobilisation and national budget allocations could be the best solution.

For shared projects, alignment between Zambia and Zimbabwe on investor participation is another important consideration.

Transmission becomes an investment priority

Securing finance is only part of the challenge. Transmission is an investment priority in its own right: generation and grid development must advance together if proposed capacity is to support reliable supply and cross-border trade.

Interconnectors can reduce the risk of stranded assets and strengthen investor confidence by opening access to a wider pool of buyers. Private developers should be seen as partners to the utilities, rather than competitors.

Regional links like ZAMTAN, ZIZABONA and ZTK are important

Cross-border cooperation must extend beyond shared ambition to the financial information and investment arrangements needed to move projects forward.

Dollar-denominated trading is a means of improving transaction efficiency and helping financiers and IPPs manage currency risk.

One of the clearest arguments for regional market credibility comes from the Southern African Power Pool (SAPP), which has settled more than USD 1 billion since 2013 without a recorded non-payment incident. This settlement record offers a concrete counterpoint to the uncertainty surrounding projects seeking finance.

Last word

The promise of Zim-Zam 2026 lies in the interaction among its three themes:

  • Connectivity gives investment a route to market.

  • Credibility gives capital a reason to commit.

  • Cooperation helps ensure that projects strengthen a regional system rather than solve isolated problems.

Success hinges on bankable projects, transmission networks capable of carrying the electricity, and viable markets that can pay for it. The true measures of progress will be the number of projects that reach financial close, functioning grid connections, and a dependable power supply that supports growth on both sides of the Zambezi.

This article was created and contributed to by Allen Leuta, partner and Head of Banking & Finance at Bowmans; Aleem Tharani, Head of Projects, Energy and Infrastructure; and partners Busisiwe Nhlapo, Ryan Kitcat, Bwalya Chilufya-Musonda, and Simonne Heunis.